sto1 - datacentre redundancy failover test
Scheduled Maintenance Report for Safespring
Completed
The scheduled maintenance has been completed.
Posted Feb 15, 2023 - 08:30 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 15, 2023 - 07:01 CET
Scheduled
Our datacentre vendor in our sto1 site will perform a redundancy failover test during working hours on thursday 15. february.

During the test, they will switch the datacentre from external power to UPS/Generator power and back. This is a routine task that is performed regularly to ensure that backup systems work as intended.

This is expected to have no impact for Safespring and our customers, as power to our racks are expected to be fully redundant during the test, but as a precaution, we will have extra personell on standby during the test period.
Posted Feb 14, 2023 - 19:02 CET
This scheduled maintenance affected: Safespring Compute.