Planned maintenance for Safespring Compute in STO1
Scheduled Maintenance Report for Safespring
Completed
The scheduled maintenance has been completed.
Posted Mar 25, 2024 - 19:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 25, 2024 - 13:00 CET
Scheduled
* Planned work:

The backend storage clusters for the compute volume service (fast and large) will be reconfigured and upgraded. This is a continuation of the work from the last similar maintenance window.

* Impact:

A low risk of intermittent i/o blocks in the fast and large volume services. Duration of blocked i/o could range from seconds up to a minute in duration. Longer blocks are not expected.

* Customer actions needed: None.
Posted Mar 18, 2024 - 09:17 CET
This scheduled maintenance affected: Safespring Compute.