Planned maintenance for Safespring Storage in sto2
Scheduled Maintenance Report for Safespring
Completed
Maintenace was completed while the service operated normally. No downtime was needed.
Posted Oct 12, 2021 - 16:59 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 12, 2021 - 09:00 CEST
Scheduled
* Planned work: We plan an expansion of the storage cluster in sto2, and this maintenance window will be used to add higher capacity network and more disk space to existing storage hardware
* Impact: The cluster will be shut down while we work on physical hardware
* Customer actions needed: None
Posted Oct 01, 2021 - 15:21 CEST
This scheduled maintenance affected: Safespring Storage.